Phases, timeline and governance

You will be able to: Lay out an ERP project in phases with stage gates; Build a realistic timeline for a small business; Set up governance: steering, status reports and decision logs.

  • Read not done yet
  • Self-check: not taken not done yet
  • Lesson complete not done yet

A project is a controlled path from agreement to a working system. Phases give it shape, stage gates give it checkpoints, and governance keeps decisions visible.

PhaseMain workGate at the end
1 PrepareKick-off, team, access, planPlan approved
2 Discover and designWorkshops, requirements, fit-gap, blueprintBlueprint signed
3 BuildConfigure Zeyto, masters, users, prints; first migrationConfiguration review
4 Migrate and testRehearsals, reconciliation, test scripts, UATUAT signed
5 Train and cut overTraining, cutover plan, final loadGo/no-go
6 Hypercare and closeSupport, first month-end, handover, closureAcceptance

What each gate checks

  • Blueprint signed: scope, fit-gap decisions and assumptions agreed by the sponsor, finance lead and process owners.
  • UAT signed: all Must scripts passed, no open severity 1 or 2 defects, accepted items listed in writing.
  • Go/no-go: opening balances reconciled and signed, users trained, backup restore-tested, support rota in place.

An example timeline: 12 users, one site, 10 weeks

WeeksActivity
1Kick-off, document collection, access
2-3Discovery workshops, requirements, fit-gap
4Blueprint review and sign-off
4-6Configuration; data cleansing by the client
6-7Migration rehearsals 1 and 2; opening balances reconciled
7-8UAT; defect fixing
8-9Training sessions; cutover preparation
9Final cutover weekend and go-live
10 onwardsHypercare and first month-end

This plan assumes the client's people are available about two hours a day. If they are not, the timeline stretches. State this assumption in the SOW.

Governance

  • Steering committee: sponsor, client lead, accountant, project manager. Meets at each gate, or every two weeks, to decide scope, budget and go/no-go.
  • Weekly status report: one page with progress, next steps, risks and decisions needed, and a red, amber or green rating.
  • Decision log: date, decision, who decided, why. It ends many arguments later.
  • Change control: described in a separate lesson.
  • Document control: version numbers and a single shared folder.
A one-page statusWeek 6, Amber. Done: configuration 90%, customers and suppliers loaded. Risk: the accountant's ageing file arrives 3 days late; recovery is possible if received by Friday. Decision needed: sponsor to confirm the second UAT tester. Next week: rehearsal 2 and UAT preparation.
TipFix the date of go-live only after the second migration rehearsal. Promising a date at kick-off, before you have seen the data, is how projects start late.

Practise in the demo

  1. Draw a six-phase plan for a 10-user client with gates and dates.
  2. List the decisions a steering committee would make at the blueprint gate.
  3. Open https://demo.zeyto.app/demo-app/ and sign in with the demo login. This is a public demo with sample data, so nothing you do there affects a real business.
Open the live demo

Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.

Key takeaways
  • Phases end in gates: blueprint, UAT and go/no-go.
  • A 12-user, one-site project typically runs about 10 weeks with client availability stated.
  • Governance means a status report, a decision log and change control.

Check yourself

3 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.

1. Which of these is a stage gate in an ERP project?

2. The project is slipping by 3 days but recovery is possible. What rating does the status report show?

3. Which TWO belong in a project's governance?

Select all that apply.