Go-live is a start, not a finish. The first two to four weeks, called hypercare, are when confidence is won or lost.

Go-live day

  • Be on site before the first user, with the cutover checklist and the quick reference cards.
  • Walk the floor: sit with each team for the first transactions.
  • Keep an issue log visible to everyone, with owner and status.
  • Hold a 10-minute end-of-day review with the client lead.

Hypercare

Agree the hypercare period in the SOW, for example 14 days after go-live. Define hours, contacts and response times. Triage every ticket into one of four classes.

ClassExampleAction
BugPosting wrong amountRaise with severity; escalate to Zeyto if it is a product fault
ConfigurationItem on the wrong VAT codeFix in settings; update the workbook
Training'How do I cancel an invoice?'Short coaching; add to the reference card
Change request'We also want a new approval step'Log it for change control
A hypercare curveTickets by week are 48, 27, 12 and 6, a total of 93. The fall from week 1 to week 4 is (48 - 6) / 48 = 87.5%. More than half of week-1 tickets were 'how do I' questions, so the team added three quick reference cards and held a 30-minute refresher for the sales reps in week 2.

The first month-end

Be present for the first month-end close. Help the accountant run bank reconciliation, check the Trial Balance, review ageing and stock reports, prepare the VAT Return Worksheet and lock the period. Problems at the first close reveal configuration errors.

When is it stable?

  • Daily tickets are below an agreed level for two consecutive weeks.
  • No open severity 1 or 2 defects.
  • The first month-end close is done with the client's own staff.
  • Backups are running and restore-tested.
  • Users complete their tasks without the consultant.

Then you move to handover. If one of the criteria is not met, extend hypercare by a defined period and say why.

Watch outA flood of tickets in week one is normal. A flood of the same ticket in week four means a training or design gap that needs fixing, not more coaching.
TipNever let the project team vanish on the day after go-live. Reduce on-site time in steps: daily, then three days, then on call.

Practise in the demo

  1. Design a hypercare ticket log with the four classes and a priority for each.
  2. In the demo, open Reports, Posting Trail and the Dashboard to see the checks you would run each evening in week 1.
  3. Open https://demo.zeyto.app/demo-app/ and sign in with the demo login. This is a public demo with sample data, so nothing you do there affects a real business.
Open the live demo

Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.

Key takeaways
  • Be on site, visible and logging every issue on go-live day.
  • Triage tickets as bug, configuration, training or change request.
  • Stability means falling tickets, no severe defects, a closed month-end and tested backups.

Check yourself

4 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.

1. What is hypercare?

2. Weekly tickets are 48, 27, 12 and 6. What is the percentage fall from week 1 to week 4?

3. Most week-one tickets are 'how do I...' questions. What does this suggest?

4. Which are sound hypercare stability criteria?

Practice questions for this module · Printable study sheet