Testing, training and go-live: study sheet

Outcomes, the key takeaway of every lesson and the key tables, on a sheet you can print or save as a PDF.

In the print dialog choose A4 and turn off “Headers and footers”. To keep a PDF, pick “Save as PDF” as the printer. The sheet prints landscape, in columns.

Zeyto Academy · Advanced · Module 25

Testing, training and go-live

Plan and run testing and UAT, train end users, execute the cutover, support hypercare, hand over to support, close the project and measure success.

You will be able to

  • Write a test plan, scripts and scenarios with ledger checks, negative cases and role tests
  • Run UAT with key users, triage defects and obtain sign-off
  • Build a role-based training plan using Zeyto's help and training database
  • Prepare a cutover plan, go-live checklist and go/no-go criteria
  • Run go-live, hypercare and stabilisation
  • Hand over to support, close the project and measure success against baselines

Test planning

  • Test by layers: configuration, process, integration, migration, roles, output, backup and UAT.
  • Every requirement needs a script; every script an expected result.
  • Severity decides what must be fixed before go-live.

Writing test scripts and scenarios

  • A script has preconditions, numbered steps, specific expected results and a ledger check.
  • Test negative cases, corrections and roles, not only the happy path.
  • Write the expected figures first.

User acceptance testing and sign-off

  • The client's key users execute UAT; the consultant supports.
  • Triage daily and retest fixes with a few related scripts.
  • Sign-off records the known state, including accepted open items.

End-user training

  • Train by role, close to go-live, with real examples.
  • Use in-product help, Ctrl+K and a training database; help is English only.
  • Check competence with a signed task checklist, not just attendance.

The cutover plan and checklist

  • The cutover plan is built from rehearsals, with an owner and time for every task.
  • Remove test data, set Live mode, activate the licence, post openings and test the backup.
  • Go/no-go uses stated criteria, not feelings.

Go-live day, hypercare and stabilisation

  • Be on site, visible and logging every issue on go-live day.
  • Triage tickets as bug, configuration, training or change request.
  • Stability means falling tickets, no severe defects, a closed month-end and tested backups.

Handover, project closure and measuring success

  • Hand over a complete pack, and show the client's administrator the support and recovery tools.
  • Close the project with acceptance, final invoice, lessons learned and archive.
  • Measure benefits against baselines agreed before the project.

Test planning: key table

Test typeWhat it provesWho tests
Configuration testEach setting is as the workbook saysConsultant
Process testA single process works from start to finish, such as quotation to receiptConsultant, then key users
Integration (end-to-end)Processes connect: a sale reduces stock, creates the receivable and VAT, and reaches the reportsConsultant and accountant
Data migration testLoaded balances reconcile to the old systemAccountant and consultant
Role and security testEach role sees and can do only what it shouldConsultant and process owners
Output testPrints, PDFs, exports and labels look right on the real printersKey users
Backup and restore testA backup can be restoredTechnical consultant
User acceptance test (UAT)The business accepts the systemClient key users

Test planning: key table

SeverityMeaningExampleResponse
1 BlockerCannot work or amounts wrongAn invoice cannot be submitted, or VAT posts to the wrong boxFix before go-live
2 MajorImportant function fails, workaround existsPrint layout cuts off the totalFix before go-live unless agreed
3 MinorSmall problemLabel wordingFix in hypercare
4 CosmeticAppearance onlySpacingBacklog

Writing test scripts and scenarios: key table

FieldContent
ID and titleTS-OTC-01, Cash-on-credit sale with VAT
Requirement IDR-02
PreconditionsCustomer C001 credit limit AED 20,000; item I-100 price AED 100, cost AED 60, stock 50; user with Sales role
StepsNumbered, one action each
Expected resultSpecific figures and screens
Ledger checkWhat Posting Trail and reports must show
Result and testerPass or Fail, name, date, defect ID

Writing test scripts and scenarios: key table

ProcessScenarioPriority
SalesQuotation to order to delivery note to invoice to receiptMust
SalesCredit limit exceededMust
SalesReturn with credit noteMust
PurchasePO to GRN to purchase invoice to paymentMust
StockTransfer between warehouses and an adjustmentShould
POSCash sale, card sale, shift closeMust for retail
FinanceReceipt allocation to oldest invoices; PDC deposit and clearanceMust
VATReturn Worksheet equals reportsMust
RolesEach role's allowed and refused actionsMust

User acceptance testing and sign-off: key table

DayFocusPeople
1Briefing, access check, sales scriptsSales manager, reps, accountant
2Purchase and stock scriptsPurchasing manager, storekeepers
3Finance, VAT, bank and role testsAccountant, finance manager
4Free-play with real examples, outputs and printingAll key users
5Retest of fixes, results review, sign-off meetingSponsor and process owners
Scan or visit zeyto.app/academy/learn/i05-testing-training-golive for the full lessons, self-checks and practice quiz.5 more tables in the lessons.Online learning material from Emeron Infospace FZE. Not a professional qualification.