The cutover plan and checklist

You will be able to: Build a cutover timeline from T-14 days to T+1; Complete a go-live checklist with owners; Set go/no-go criteria.

  • Read not done yet
  • Self-check: not taken not done yet
  • Lesson complete not done yet

The cutover plan is the minute-by-minute script of the move to live. It is built from the rehearsals and owned by the project manager, with one named person for each task.

WhenActivityOwner
T-14 daysUAT signed; go-live date confirmed; freeze on configuration changesProject manager
T-10Training finished; competence checklists signedConsultant
T-7Second migration rehearsal reconciled; printers tested on every tillConsultant, technical
T-3Production server installed, licence ready, users created, backup destination testedTechnical consultant
T-1Communication to staff, customers, suppliers; old system freeze time confirmedSponsor
T-0Final extract, load, reconcile, sign, go/no-goTeam
T+1Staff start; consultants on site; first-day issue logAll

Go-live checklist

ItemWhereDone by
Company profile, fiscal years, tax codes verified against the workbookSettingsConsultant
Test transactions removedSettings, Reset Company Data (takes a verified backup first; keeps users, settings and company profile)Consultant
Data Mode is LiveSettings, Data Mode (Live/Demo)Technical
Licence activated and Seats & Limits checked; Zeyto Edge restartedSettings, LicenseTechnical
Opening balances posted and reconciliation signedAccounting, OpeningsAccountant
Users and roles created; strong passwords; POS PINsSettings, Users & Permissions and Security PolicyConsultant
Daily automatic backup on; off-computer copy; one restore testSettings, BackupTechnical
Printers, labels and paper tested on every PC and tillSettings, Printers and TemplatesTechnical
Remote access set up where agreedSettings, Remote & Mobile AccessTechnical
Old system set read-only and archivedClient ITClient IT
Support contacts and escalation list issuedHandover packProject manager

Go/no-go criteria

  • UAT signed with no open severity 1 or 2 defects.
  • Opening balances reconciled and signed by the accountant.
  • At least 90% of users trained and signed on their checklist.
  • Backup taken and restore-tested.
  • Support rota for the first two weeks confirmed.
A no-go that saved the launchAt T-1 the restore test of the first backup failed because the backup drive had a permissions problem. The team fixed the drive and repeated the restore the same day. If this had been found after go-live, a day of live data would have had no safe copy.
Watch outDo not activate the licence and then wipe the computer. Restore first, activate second, and keep a copy of the licence key from the customer portal.

Practise in the demo

  1. Draft a cutover timeline for your own imaginary client with owners and a go/no-go time.
  2. Open Settings, then License and Backup in the demo and identify the checklist items they support.
  3. Open https://demo.zeyto.app/demo-app/ and sign in with the demo login. This is a public demo with sample data, so nothing you do there affects a real business.
Open the live demo

Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.

Key takeaways
  • The cutover plan is built from rehearsals, with an owner and time for every task.
  • Remove test data, set Live mode, activate the licence, post openings and test the backup.
  • Go/no-go uses stated criteria, not feelings.

Check yourself

4 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.

1. Which action belongs to the cutover steps for activating a renewed licence?

2. Which TWO items belong on the go-live checklist?

Select all that apply.

3. Two days before go-live the rehearsal trial balance shows 120,000 unexplained on the Opening Balance ledger. What is the right decision?

4. Test transactions were entered in the live company before cutover. Which Zeyto tool clears them while keeping users and settings?

Practice questions for this module · Printable study sheet