Recording a production run
You will be able to: Post a Production Entry correctly; Calculate component quantities when the run is not a whole batch; Review what was posted.
- Read not done yet
- Self-check: not taken not done yet
- Lesson complete not done yet
Production Entry is where a BOM becomes real stock movement. There is no draft: Produce posts at once. Check the quantity and warehouse before you press it.
The steps
- Open Inventory ▸ Production Entry. Pick the Finished Item (BOM): only items with an active BOM are offered.
- Type Qty to Produce. The Components to Consume grid previews how much of each component the run will use.
- Pick the Warehouse. Components come out of it and finished goods go into it. Check the Date, which must fall in an open fiscal year.
- Press Produce. The status changes to Posted and a note shows the entry number.
Zeyto scales the recipe: each component is its BOM quantity × Qty to Produce ÷ the BOM's Qty per Batch, rounded to four decimals. The grid is a preview; Zeyto recalculates when you press Produce.
What is posted
- Stock: each component out of the warehouse, the finished item in.
- Ledger: Inventory is credited for the components and debited for the finished goods through WIP Clearing (1160), which nets to zero.
- No expense, no VAT, no profit or loss.
The Production Entries register lists runs newest first (default This month). View opens a read-only side panel with the components used and the finished item. The Total column adds the components and the finished goods, so it reads about twice the batch cost: in the cake example 81.00 + 81.00 = 162.00. For the real cost use the Stock Ledger / Movement report.
When a run is refused
- The Date is in a closed fiscal year.
- A component would go below zero while Settings ▸ Costing blocks negative stock.
- The item has no active BOM.
A refused run may leave a Draft row in the register. It changes no stock, and View is all you can do with it.
Try it in the demo
- Open Inventory ▸ Production Entry in the demo and pick an item with a BOM; read the Components to Consume preview (do not press Produce on shared demo data).
- Calculate by hand the components for a quantity that is not a whole batch.
- Open the Production Entries list and compare the Total column with the real batch cost.
Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.
- Produce posts at once: components out, finished goods in at their total cost.
- Component qty = BOM qty × Qty to Produce ÷ Qty per Batch, to four decimals.
- The Total column reads about twice the cost.
- Correct mistakes with a Stock Adjustment.
Check yourself
5 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.