Delivery, inspection and the goods receipt
You will be able to: Follow a delivery from scheduling to closing; Apply the rule that pass + conditional + reject + hold equals counted; Show how the supplier invoice treats accepted and not accepted goods.
- Read not done yet
- Self-check: not taken not done yet
- Lesson complete not done yet
A delivery is scheduled against a submitted order. It moves through scheduled, dispatched, arrived, unloading, awaiting inspection, inspected and closed. It can be cancelled before arrival, or rejected at the gate after it arrives. Goods are received into stock at the quantity the inspection accepted.
At the gate you count the goods. The inspection then records, per line, the quantity that passes, the quantity accepted with a deviation (conditional), the quantity rejected and the quantity held. The four must add up to the counted quantity. A conditional acceptance needs the deviation written down. A rejection needs a reason.
- A critical check that fails means the goods cannot be passed or accepted conditionally. Reject or hold them.
- If the item needs a test certificate, it must be attached before the goods pass.
- If the item needs an approved sample, the submittal must be approved first.
- A rejection or an accepted deviation creates a non-conformance report automatically.
When the inspection is decided, the goods receipt takes only the accepted quantity. The system refuses a receipt for more than was accepted. Goods on hold wait in custody and are not stock; they are later resolved as pass or reject. Rejected goods go back to the supplier on a return.
The three-way view
The three-way view per order line shows the quantity ordered, delivered and counted, accepted, rejected, held and billed, and the quantity still billable, which is accepted less billed. A claim on the supplier (short supply, re-delivery, rework) is credited to the account where the cost was booked once the supplier issues a credit note.
Walk it through
- Split a counted quantity of your own between pass, reject and hold and check the sum.
- Compute the value of the part of an invoice that is not accepted.
- In the demo, open Delivery and inspection and see the Inspection templates and Supplier claims tabs.
Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.
- Pass + conditional + reject + hold equals counted.
- The receipt cannot exceed the accepted quantity; held goods are not stock.
- The not-accepted part of an invoice waits for the credit note.
Check yourself