Procurement, subcontracts and site control: study sheet

Outcomes, the key takeaway of every lesson and the key tables, on a sheet you can print or save as a PDF.

In the print dialog choose A4 and turn off “Headers and footers”. To keep a PDF, pick “Save as PDF” as the printer. The sheet prints landscape, in columns.

Zeyto Academy · Advanced · Module 44

Procurement, subcontracts and site control

Buy, receive and inspect material, certify subcontractors and control site stores, petty cash and labour (Zeyto Construction & Contracting, pre-release).

You will be able to

  • Follow a project purchase from request to paid invoice
  • Compare quotes on landed rate and apply award and tolerance rules
  • Apply the inspection rule and read the invoice treatment of not-accepted goods
  • Control site stores, issues and phones
  • Certify a subcontractor with retention cap, advance recovery and back-charges
  • Run petty cash, timesheets and the payroll allocation

The buying chain for a project

  • The chain is request, reserve, RFQ, award, delivery and inspection, goods receipt, invoice.
  • Reserve first; only the shortfall is bought.
  • Every document carries the project and the item of work.

RFQ, comparison and order control

  • Compare landed rates, not unit prices.
  • A non-lowest award needs a written reason and an approver.
  • Order and invoice rates are both checked against a tolerance.

Delivery, inspection and the goods receipt

  • Pass + conditional + reject + hold equals counted.
  • The receipt cannot exceed the accepted quantity; held goods are not stock.
  • The not-accepted part of an invoice waits for the credit note.

Site stores, issues and the phone app

  • Issues above BOQ need a reason and an approver.
  • Returns come back at the cost they left at, never above what was issued.
  • A phone is trusted only after an administrator approves it.

Subcontracts: measure, certify, pay

  • Activation needs live insurance and licence and items within the value.
  • Retention = 10% of gross, limited by cap room; advance recovery = advance % of gross.
  • Certificates move measured, site approved, PM approved, billed.

Site costs: petty cash and people

  • Petty cash: receipt photo, limit, post, refill.
  • Timesheets: site engineer then project manager; the entrant never approves.
  • Payroll allocation moves only the project share of hours; bench hours stay put.

RFQ, comparison and order control: key table

SupplierUnit priceFreight per bagLanded rateTotal for 900 bags
A18.500.0018.5016,650
B17.801.1018.9017,010
C17.200.6017.8016,020

Site stores, issues and the phone app: key table

MovementRule
Issue to an itemIssues from the store to the item at the stock value. Above the BOQ quantity it needs a reason and an approver. The store cannot go negative when the stock policy blocks it.
Return to storeBrings material back at the cost it left at, never above what was issued
Transfer between storesMay go through a transit store; the receiver cannot confirm more than was sent
DamageA damage report posts the wastage and can raise a back-charge
Local purchaseOne-step purchase invoice; the payer is petty cash, cash advance, card or supplier credit; a voucher over the limit needs an approver

Subcontracts: measure, certify, pay: key table

LineCertificate 1Certificate 2
Measured work1,500 m2 block, 2,000 m2 plaster500 m2 block, 2,000 m2 plaster, 1,000 m2 paint
Gross this period160,000170,000
Retention 10% (cap room)16,000 (20,000 left)4,000 (only 4,000 left; 10% would be 17,000)
Advance recovery 10%16,00017,000
Taxable (gross less retention)144,000166,000
VAT 5%7,2008,300
Bill total before advance151,200174,300