Projects change. The product handles change by recording it as new versions, never by overwriting. There are three kinds of budget change and one kind of schedule change to know.

ChangeWhat it doesApproval
Budget transferMoves budget between two items of the same project, total unchangedTwo approvers, neither the creator
Budget revisionChanges the project total, for example after an approved variationTwo approvers, neither the creator
Contingency drawdownMoves budget from the project's contingency item to another item; the pool keeps an original, a drawn and a floor amountA kind of budget transfer: two approvers
Schedule baselineA frozen copy of the plan's dates kept beside the current planTaken by the planner; earlier baselines stay

All budget changes are non-posting: a budget reads the ledger and never writes to it. The approvals use the same engine as other records, so a configured approval matrix for the record type wins over the default of two different non-creators. Company settings can relax the four-eyes rule to one approver, but that is a control decision.

A variation changes both sidesA project has a contract of AED 2,000,000 and a budget of AED 1,700,000 (margin 15%). The client approves a variation of AED 100,000 priced to cost AED 85,000. The contract becomes AED 2,100,000. You raise a budget revision adding AED 85,000, so the budget becomes AED 1,785,000. The margin is (2,100,000 - 1,785,000) / 2,100,000 = 15%, unchanged. If the variation had been priced at AED 100,000 for cost 95,000, the margin on the variation would be only 5%.

Forecast snapshots

A forecast snapshot freezes budget, committed, actual, estimate to complete, forecast and variance as at a date, for the project and for each item. You take one every month and confirm it; a confirmed snapshot is frozen. Each snapshot splits the variance by cause (price, scope or other). In version 1, quantity and productivity causes are not calculated and fall into other. Comments can be added to a snapshot for the discussion.

The Forecast view inside the Finance tab of a project where a forecast snapshot freezes budget, committed, actual and forecast as at a date.

Finance tab, Forecast: snapshots of the project as at a date.

Finance tab, Forecast: snapshots of the project as at a date.
Watch outA schedule baseline is not a budget baseline. Taking a new schedule baseline after an approved variation resets the slip shown on the Gantt chart; do not do it to hide delay. The earlier baselines stay in the history.
TipUse the same date for the forecast snapshot, the WIP run and the month-end close, so the reports can be compared line by line.

Walk it through

  1. Write one example of each: a transfer, a revision and a contingency drawdown, with amounts.
  2. Compute the margin of a variation priced at 100,000 with cost 95,000 and its effect on the project margin.
  3. In the demo, open a project's Finance tab and look at the list of budget changes and the forecast snapshots.
Open the live demo

Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.

Key takeaways
  • Budget changes are new versions, approved by two people, and never post to the ledger.
  • A transfer keeps the total; a revision changes it.
  • Forecast snapshots freeze the numbers monthly with a cause split.

Check yourself

5 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.

1. A budget transfer between two items:

2. A forecast snapshot, once confirmed, can still be edited.

3. A variation adds AED 100,000 to the contract and AED 85,000 to the budget. What is the new budget if it was AED 1,700,000?

4. A variation of AED 100,000 costs AED 95,000 to deliver. What is its margin on sell?