The budget: by item, by nature, in versions
You will be able to: Explain how a budget is stored and approved; Distinguish the original baseline budget from the current budget; Check how much of an item's budget is still available.
- Read not done yet
- Self-check: not taken not done yet
- Lesson complete not done yet
The budget is what you plan to spend, set per item of work and per cost nature, in versions. Estimate, contract and budget are different things: the estimate is your price build-up, the contract BOQ is what the client agreed, and the budget is the cost you commit to control against. At the award the first budget equals the estimate cost, but they can diverge: the budget may be tighter than the estimate, for instance after a buying gain.
Versions and approval
- A budget version moves from draft to submitted to approved. Only a draft can be edited; to change an approved budget you start a revision, which copies the current figures.
- Approving makes the version the current budget (one current budget per project) and supersedes the previous current one.
- The first approved baseline stays as the locked original forever. Later versions are revisions.
- Amounts cannot be negative, and each node takes one amount per nature and version.
On the node page the Budget tab lets you type the amounts for an item by nature; saving puts them in the latest draft version, creating one if none exists.
How much is still available
The Finance tab (budget control) compares for each item and nature the budget, the commitments still open, and the actual cost posted. The money available to an item or nature is budget less actual less open commitments. This is the figure that decides whether a transfer of budget from that item is possible.
Walk it through
- For one item write a budget by nature (six natures) that adds to the item's cost.
- Compute the available budget for an item after you add assumed actual and committed amounts.
- In the demo, open a project's Budget tab, create a draft version, and look at how the current approved version differs.
Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.
- A budget is by item, by nature and in versions.
- Only a draft can be edited; approving makes a version current; the original baseline is kept.
- Available = budget - actual - open commitments.
Check yourself
3 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.