BOQ, estimating and budget: study sheet

Outcomes, the key takeaway of every lesson and the key tables, on a sheet you can print or save as a PDF.

In the print dialog choose A4 and turn off “Headers and footers”. To keep a PDF, pick “Save as PDF” as the printer. The sheet prints landscape, in columns.

Zeyto Academy · Core · Module 42

BOQ, estimating and budget

Build a priced BOQ, estimate from rates, lock a contract baseline and control it with budget versions (Zeyto Construction & Contracting, pre-release).

You will be able to

  • Explain the BOQ as the items of the breakdown and compute sell, cost and margin
  • Organise cost by category and by the six cost natures
  • Price an estimate item in Zeyto's fixed order and read the rounded sell rate
  • Describe BOQ version states and what locking and award do
  • Set, approve and check a budget by nature, and know the available amount
  • Treat revisions, transfers, forecasts and baselines as new versions

The bill of quantities in Zeyto

  • The BOQ is the set of items of the breakdown, not a separate file.
  • Sell amount and cost amount are quantity times rate, and their difference is the planned margin.
  • Check margin by line as well as in total.

Categories, codes and the six cost natures

  • Two slices: where (item of work) and what kind (nature).
  • The six natures are material, own labour, machines, subcontract, third-party manpower and other.
  • Copying a category into a project detaches it from the master.

Building an estimate from rates

  • Pricing has a fixed order: direct, allowance, adders, cost, overhead then profit, rounded rate.
  • Wastage lives inside component unit costs.
  • Quotes are compared on comparable cost, including retention, advance, camp and permit terms.

From tender to a locked contract baseline

  • Draft, submitted, accepted, locked: only locked is the baseline.
  • A locked BOQ is changed only through a variation order.
  • The award builds project, BOQ, budget, schedule, contract and clauses in one go.

The budget: by item, by nature, in versions

  • A budget is by item, by nature and in versions.
  • Only a draft can be edited; approving makes a version current; the original baseline is kept.
  • Available = budget - actual - open commitments.

Revisions, transfers, contingency and baselines

  • Budget changes are new versions, approved by two people, and never post to the ledger.
  • A transfer keeps the total; a revision changes it.
  • Forecast snapshots freeze the numbers monthly with a cause split.

The bill of quantities in Zeyto: key table

ItemQtyUnitSell rateSell amountCost rateCost amount
Excavation in soil800m34536,0003225,600
Concrete C40250m3620155,000505126,250
Reinforcement steel30t3,900117,0003,25097,500
Blockwork 200 mm1,400m278109,2006185,400
Cement plaster2,800m236100,8002775,600
Total518,000410,350

Categories, codes and the six cost natures: key table

NatureWhat it coversHow cost reaches it
MaterialGoods bought or taken from stockPurchase invoices and stock issues to the item
Own labourYour own staffTimesheets and the monthly labour allocation
MachinesYour own plant and equipmentCharge-out, fuel and parts, or depreciation allocation
SubcontractWork done by a subcontractorSubcontract bills (certificates)
Third-party manpowerWorkers supplied by an agencyAgency bills matched to approved timesheets
OtherEverything else, including commercial addersService purchases, petty cash, other journals

From tender to a locked contract baseline: key table

StateMeaningWhat can still change
DraftBeing pricedQuantities and rates
SubmittedSent to the clientCan go back to draft, or be accepted or lost
AcceptedClient agreedCan be locked or superseded
LockedThe contract baselineOnly through a variation order

Revisions, transfers, contingency and baselines: key table

ChangeWhat it doesApproval
Budget transferMoves budget between two items of the same project, total unchangedTwo approvers, neither the creator
Budget revisionChanges the project total, for example after an approved variationTwo approvers, neither the creator
Contingency drawdownMoves budget from the project's contingency item to another item; the pool keeps an original, a drawn and a floor amountA kind of budget transfer: two approvers
Schedule baselineA frozen copy of the plan's dates kept beside the current planTaken by the planner; earlier baselines stay