BOQ, estimating and budget
Build a priced BOQ, estimate from rates, lock a contract baseline and control it with budget versions (Zeyto Construction & Contracting, pre-release).
You will be able to
- Explain the BOQ as the items of the breakdown and compute sell, cost and margin
- Organise cost by category and by the six cost natures
- Price an estimate item in Zeyto's fixed order and read the rounded sell rate
- Describe BOQ version states and what locking and award do
- Set, approve and check a budget by nature, and know the available amount
- Treat revisions, transfers, forecasts and baselines as new versions
The bill of quantities in Zeyto
- The BOQ is the set of items of the breakdown, not a separate file.
- Sell amount and cost amount are quantity times rate, and their difference is the planned margin.
- Check margin by line as well as in total.
Categories, codes and the six cost natures
- Two slices: where (item of work) and what kind (nature).
- The six natures are material, own labour, machines, subcontract, third-party manpower and other.
- Copying a category into a project detaches it from the master.
Building an estimate from rates
- Pricing has a fixed order: direct, allowance, adders, cost, overhead then profit, rounded rate.
- Wastage lives inside component unit costs.
- Quotes are compared on comparable cost, including retention, advance, camp and permit terms.
From tender to a locked contract baseline
- Draft, submitted, accepted, locked: only locked is the baseline.
- A locked BOQ is changed only through a variation order.
- The award builds project, BOQ, budget, schedule, contract and clauses in one go.
The budget: by item, by nature, in versions
- A budget is by item, by nature and in versions.
- Only a draft can be edited; approving makes a version current; the original baseline is kept.
- Available = budget - actual - open commitments.
Revisions, transfers, contingency and baselines
- Budget changes are new versions, approved by two people, and never post to the ledger.
- A transfer keeps the total; a revision changes it.
- Forecast snapshots freeze the numbers monthly with a cause split.
The bill of quantities in Zeyto: key table
| Item | Qty | Unit | Sell rate | Sell amount | Cost rate | Cost amount |
|---|---|---|---|---|---|---|
| Excavation in soil | 800 | m3 | 45 | 36,000 | 32 | 25,600 |
| Concrete C40 | 250 | m3 | 620 | 155,000 | 505 | 126,250 |
| Reinforcement steel | 30 | t | 3,900 | 117,000 | 3,250 | 97,500 |
| Blockwork 200 mm | 1,400 | m2 | 78 | 109,200 | 61 | 85,400 |
| Cement plaster | 2,800 | m2 | 36 | 100,800 | 27 | 75,600 |
| Total | 518,000 | 410,350 |
Categories, codes and the six cost natures: key table
| Nature | What it covers | How cost reaches it |
|---|---|---|
| Material | Goods bought or taken from stock | Purchase invoices and stock issues to the item |
| Own labour | Your own staff | Timesheets and the monthly labour allocation |
| Machines | Your own plant and equipment | Charge-out, fuel and parts, or depreciation allocation |
| Subcontract | Work done by a subcontractor | Subcontract bills (certificates) |
| Third-party manpower | Workers supplied by an agency | Agency bills matched to approved timesheets |
| Other | Everything else, including commercial adders | Service purchases, petty cash, other journals |
From tender to a locked contract baseline: key table
| State | Meaning | What can still change |
|---|---|---|
| Draft | Being priced | Quantities and rates |
| Submitted | Sent to the client | Can go back to draft, or be accepted or lost |
| Accepted | Client agreed | Can be locked or superseded |
| Locked | The contract baseline | Only through a variation order |
Revisions, transfers, contingency and baselines: key table
| Change | What it does | Approval |
|---|---|---|
| Budget transfer | Moves budget between two items of the same project, total unchanged | Two approvers, neither the creator |
| Budget revision | Changes the project total, for example after an approved variation | Two approvers, neither the creator |
| Contingency drawdown | Moves budget from the project's contingency item to another item; the pool keeps an original, a drawn and a floor amount | A kind of budget transfer: two approvers |
| Schedule baseline | A frozen copy of the plan's dates kept beside the current plan | Taken by the planner; earlier baselines stay |