Building an estimate from rates
You will be able to: Follow the fixed order in which Zeyto prices an estimate item; Compute the unit cost, cost and sell rate of an item; Use quotes and the rate library to support the numbers.
- Read not done yet
- Self-check: not taken not done yet
- Lesson complete not done yet
An estimate in Zeyto Construction & Contracting is a tree of groups and priced items. Each item is built up from components taken from the rate library: materials, labour, plant, subcontract and preliminaries. The library holds rates, productivity norms (crew size divided by output per hour, which turns a quantity into labour hours) and assemblies, which are saved build-ups you copy onto an item.
The fixed pricing order
- Direct cost: quantity times the sum of the component unit costs. A component's unit cost already includes its wastage: quantity per unit times (1 + wastage) times rate.
- Allowance: the risk and escalation percentages applied to the direct cost, kept in the same nature.
- Adders: bonds, insurance, labour camp, visas, permits and similar are shared over the included items in proportion to cost and booked to the nature Other.
- Cost: the sum of the nature amounts, so the budget by nature adds up to the cost exactly.
- Overhead then profit on cost: sell = cost x (1 + overhead%) x (1 + profit%).
- Sell rate is rounded to two decimals (a tender rate is quoted in fils), and the sell amount is quantity times that rounded rate.
The cost of this item is then the baseline budget when you win: material AED 49,440, own labour AED 10,300 and other AED 1,260, which add up to AED 61,000.
Quotes and options
- Quotes from subcontractors and suppliers are entered per item with the UAE terms that change the real price: retention, advance and guarantee, insurance, labour camp and visa, and permit fees. The comparable cost adds those lines to the price so that offers can be compared fairly.
- Selecting a quote puts its comparable cost into the item's build-up. Choosing a blocked supplier, a supplier graded D, or a dearer offer needs a written reason.
- An optional item that is not accepted is priced and shown but left out of every total, the budget and the award.
Walk it through
- Recompute the example with overhead 6% and profit 8% and a different adder.
- Check that your own unit cost includes wastage inside each component.
- In the demo, open an estimate item and press Build-up. Without access, build a one-line estimate in a spreadsheet using the six steps.
Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.
- Pricing has a fixed order: direct, allowance, adders, cost, overhead then profit, rounded rate.
- Wastage lives inside component unit costs.
- Quotes are compared on comparable cost, including retention, advance, camp and permit terms.
Check yourself
5 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.