Module 42 · Core · 8 min read

Categories, codes and the six cost natures

You will be able to: Use categories and codes to organise a breakdown; Name the six cost natures and map a cost to its nature; Explain why the breakdown and the natures are two different ways of slicing cost.

  • Read not done yet
  • Self-check: not taken not done yet
  • Lesson complete not done yet

You slice a project's cost in two directions. One direction is where it is spent: the item of work (the breakdown, with its codes). The other direction is what kind of cost it is: the nature. A good control system keeps both, because overruns have a place and a cause.

Categories and codes

The Category Master is your library of work categories. You build it once, for example Finishes, then Flooring, then Tiling, then the items. A category can go as deep as you need, with a warning above 6 levels and a limit of 12. Codes such as D1 and D1.1 are numbered for you. Each category has a type: a group (it has sub-categories) or an item (it takes cost and quantities), and each item can have a default cost nature. A project copies a branch with Copy into project and from then on no longer follows the master, so a change in the master never moves a running job.

The Category Master listing work categories as a tree with their codes.

Category Master: build the library of work categories once.

Category Master: build the library of work categories once.

The six cost natures

NatureWhat it coversHow cost reaches it
MaterialGoods bought or taken from stockPurchase invoices and stock issues to the item
Own labourYour own staffTimesheets and the monthly labour allocation
MachinesYour own plant and equipmentCharge-out, fuel and parts, or depreciation allocation
SubcontractWork done by a subcontractorSubcontract bills (certificates)
Third-party manpowerWorkers supplied by an agencyAgency bills matched to approved timesheets
OtherEverything else, including commercial addersService purchases, petty cash, other journals
Same cost, two slicesAn invoice for AED 12,000 of concrete is posted to item C2.1 Slab, nature material. A second invoice for AED 9,000 from a pouring gang is posted to the same item, nature subcontract. On the item C2.1 the actual cost is AED 21,000. Sliced by nature the cost shows material 12,000 and subcontract 9,000. If the budget for the item was 14,000 material and 4,000 subcontract, the item is over budget in total by 3,000, but the real problem is subcontract at 5,000 over, partly hidden by a 2,000 saving on material.

The ledger accounts that receive the cost are the project cost accounts the product installs (materials, labour, machines, subcontract, third-party manpower and others) and are mapped to the natures. You do not choose the nature by typing it on each journal; it follows from the account and the kind of document.

Watch outPut overheads (office, management salaries) outside the breakdown unless you decide to allocate them. A project carries an overhead allocation percent setting, but the allocation is a management choice and should not be mixed into item costs by accident.
TipKeep the number of items per project manageable. Many hundred items give detailed control but cost time in progress entry. A common compromise is one item per BOQ line group that you bill and control separately.

Walk it through

  1. Draw a three-level category tree for finishes, with at least six items.
  2. For each item, write the main cost nature.
  3. In the demo, open the Category Master and add a category with its Arabic name, then see the code that was given.
Open the live demo

Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.

Key takeaways
  • Two slices: where (item of work) and what kind (nature).
  • The six natures are material, own labour, machines, subcontract, third-party manpower and other.
  • Copying a category into a project detaches it from the master.

Check yourself

2 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.

1. Which is NOT one of the six cost natures?

2. The Category Master is:

Practice questions for this module · Printable study sheet