Module 45 · Advanced · 9 min read

Estimate at completion and earned value

You will be able to: Distinguish the three forecasts in the product; Compute CPI, SPI, EAC, ETC and VAC from BAC, EV, PV and AC; Read the portfolio colour bands.

  • Read not done yet
  • Self-check: not taken not done yet
  • Lesson complete not done yet

Zeyto Construction & Contracting gives you three ways to see the final cost, and they answer different questions.

The Cost to Complete report showing for each project the budget, actual, committed and the forecast final cost.

Reports, Cost to Complete.

Reports, Cost to Complete.
  • Row forecast: for each item and nature, actual + committed + ETC. The sum is the control view's forecast.
  • Earned value EAC: budget at completion divided by the cost performance index. It assumes the cost efficiency so far continues.
  • Approved estimate at completion: cost to date plus an estimate to complete that a person types, then an authorised user approves. It drives revenue on the cost basis (next lesson) and must be approved before it counts.

The earned value figures come from the BOQ weights and the ledger. BAC is the sum of the current budget. EV is each row's budget times its progress. AC is the actual cost. PV is BAC times the planned share of the work today from the latest baseline of the schedule.

MeasureFormulaOur example
BACSum of the current budget850,000
EVBudget x progress %850,000 x 40% = 340,000
ACActual cost360,000
PVBAC x planned %850,000 x 45% = 382,500
CPIEV / AC0.9444
SPIEV / PV0.8889
EACBAC / CPI900,000
ETCEAC - AC540,000
VACBAC - EAC-50,000
Cost varianceEV - AC-20,000
Schedule varianceEV - PV-42,500

With CPI 0.9444 the project is spending about 1.06 for every 1.00 of work done, so the EAC is 900,000, 50,000 above the budget. Against a contract value of 1,000,000 the forecast margin is (1,000,000 - 900,000) / 1,000,000 = 10%.

The colour bands

The portfolio board shows each project as a tile whose big chip is the worst of six checks. Schedule uses SPI: green from 0.95, amber from 0.85, red below. Cost uses CPI in the same bands. Margin is green from 8% and amber from 3%. Cash is the net billed divided by cost to date: green from 1, amber from 0.8. Safety and quality use incident, permit, NCR and RFI rules.

The Portfolio board where each project tile shows the schedule, cost, margin and cash chips in red, amber or green.

The colour bands on the Portfolio board.

The colour bands on the Portfolio board.

Our project: CPI 0.9444 is amber, SPI 0.8889 is amber, margin 10% is green, and cash is 330,000 / 360,000 = 0.92, amber. The tile is amber overall because the worst check decides.

Watch outAn EAC from CPI is a statistic, not a promise. When an approved estimate to complete exists, compare the two and write down why they differ.

Walk it through

  1. Compute CPI, SPI and EAC for your own project with BAC, EV, PV and AC.
  2. State which band each index falls into.
  3. In the demo, open the Portfolio board and read the small earned value table on a tile.
Open the live demo

Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.

Key takeaways
  • Three forecasts: row forecast, CPI-based EAC, approved estimate at completion.
  • CPI = EV / AC; SPI = EV / PV; EAC = BAC / CPI.
  • The tile colour is the worst of six checks.

Check yourself

4 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.

1. CPI is calculated as:

2. An SPI of 0.80 falls in the green band.

3. BAC 850,000, EV 340,000, AC 360,000. The CPI is:

4. With CPI at that level the earned value EAC (BAC / CPI) is:

Practice questions for this module · Printable study sheet