Project cost control and reporting: study sheet

Outcomes, the key takeaway of every lesson and the key tables, on a sheet you can print or save as a PDF.

In the print dialog choose A4 and turn off “Headers and footers”. To keep a PDF, pick “Save as PDF” as the printer. The sheet prints landscape, in columns.

Zeyto Academy · Advanced · Module 45

Project cost control and reporting

Control cost by item and nature, forecast to completion, recognise revenue, read WIP and close the month (Zeyto Construction & Contracting, pre-release).

You will be able to

  • Compute budget, committed, actual, ETC, forecast and variance by item and nature
  • Compute CPI, SPI, EAC, ETC and VAC and read the portfolio colour bands
  • Compute earned revenue, over or under billing and a loss provision
  • Read profitability and build a 13-week cash forecast
  • Choose the right report for a management question
  • Describe the approval rules and run the month-end close

Budget, committed and actual by item

  • Forecast = actual + committed + ETC; variance = budget - forecast.
  • ETC = budget x (1 - progress) - committed, floored at zero.
  • Read nature by nature; totals hide overruns.

Estimate at completion and earned value

  • Three forecasts: row forecast, CPI-based EAC, approved estimate at completion.
  • CPI = EV / AC; SPI = EV / PV; EAC = BAC / CPI.
  • The tile colour is the worst of six checks.

Revenue, WIP and over or under billing

  • Four methods: A billing, B percent of completion, C straight line, D point in time.
  • Earned (B, cost) = contract value x cost / EAC; over or under = billed - earned.
  • Provision = expected loss less loss already in the numbers.

Profitability and the 13-week cash forecast

  • Profitability = contract value less forecast cost; billed net less cost shows funding.
  • The 13-week forecast marks the first negative closing week.
  • Read receivables and retention separately.

The reports and the views that matter

  • Choose the report by the question.
  • WIP reads snapshots; run the revenue first.
  • Read profitability, cost to complete and WIP as a set.

Controls, approvals and the month-end close

  • One ledger with guards: leaf item, right project, project open, cost not locked.
  • The creator never approves; rejections need a reason; nothing auto-approves.
  • The close checks drafts, approvals, revenue runs, WIP and retention, then locks.

Budget, committed and actual by item: key table

NumberMeaning in Zeyto Construction & Contracting
BudgetThe amount in the current approved budget version for that item and nature
CommittedWhat is on order and still open: purchase orders for materials and open subcontract value
ActualLedger debits less credits tagged to the item and nature, up to the date you choose
Estimate to complete (ETC)Budget x (1 - item progress %) less committed, never below zero
ForecastActual + committed + ETC
VarianceBudget - forecast; negative means an overrun

Estimate at completion and earned value: key table

MeasureFormulaOur example
BACSum of the current budget850,000
EVBudget x progress %850,000 x 40% = 340,000
ACActual cost360,000
PVBAC x planned %850,000 x 45% = 382,500
CPIEV / AC0.9444
SPIEV / PV0.8889
EACBAC / CPI900,000
ETCEAC - AC540,000
VACBAC - EAC-50,000
Cost varianceEV - AC-20,000
Schedule varianceEV - PV-42,500

Profitability and the 13-week cash forecast: key table

CheckGreenAmberRed
Margin (forecast)8% and above3% to below 8%Below 3%
Cash (net billed / cost)1.0 and above0.8 to below 1.0Below 0.8

Profitability and the 13-week cash forecast: key table

WeekReceiptsPaymentsClosing balance
Opening120,000
140,00090,00070,000
250,000110,00010,000
330,00085,000-45,000
4180,00060,00075,000

The reports and the views that matter: key table

QuestionReportWhat it shows
Which project is losing money?Project ProfitabilityContract value, budget, committed, actual, forecast and margin per project
Which nature will overrun?Cost to CompleteBudget, committed, actual and ETC per nature; negative variance is an overrun
Are we over- or under-billed?Work in Progress (WIP)The latest snapshot of each project: billed against earned
Who holds our money?RetentionRetention held from the client and held back from subcontractors, releases, next due
What must we buy?Material StatusPer material: BOQ, requested, ordered, received, reserved, consumed and short
Are we paying above the BOQ rate?Purchase Price VarianceEach purchase against the BOQ rate, last price and average; negative extra cost is a saving
Is this supplier reliable?Delivery and InspectionDays late, pass percent, rejected quantities and NCRs per delivery
Which subcontract needs chasing?Subcontract StatusValue, certified, retention held, to certify, expired papers
How many hours did we use?ManpowerTimesheet hours and gate check-in hours by project and month
Is plant idle?Equipment UtilisationWorked, standby and breakdown hours, and charge-out
How safe are we?Health and SafetyIncidents, lost time, man-hours, frequency rate, permits, toolbox talks
Scan or visit zeyto.app/academy/learn/k05-project-cost-reporting for the full lessons, self-checks and practice quiz.Online learning material from Emeron Infospace FZE. Not a professional qualification.