Discovery, fit-gap and the Business Blueprint: study sheet

Outcomes, the key takeaway of every lesson and the key tables, on a sheet you can print or save as a PDF.

In the print dialog choose A4 and turn off “Headers and footers”. To keep a PDF, pick “Save as PDF” as the printer. The sheet prints landscape, in columns.

Zeyto Academy · Core · Module 22

Discovery, fit-gap and the Business Blueprint

Run discovery, gather testable requirements, map as-is and to-be, do an honest fit-gap against Zeyto, estimate, and write the Business Blueprint and SOW.

You will be able to

  • Run discovery workshops and capture real process, pain points and exceptions
  • Write testable, prioritised, traceable requirements
  • Map as-is and to-be processes and quantify the benefit
  • Classify requirements against Zeyto as standard, configuration, process change, workaround or custom request
  • Scope and estimate an ERP project with three-point estimates and contingency
  • Produce a Business Blueprint, obtain sign-off and write a proposal or statement of work

Running discovery workshops

  • Ask for real documents before the workshop and invite the people who do the work.
  • Ask people to show last week's real example, then probe exceptions.
  • Do not design or promise in the room. Send notes within one working day.

Requirements gathering

  • A requirement is testable; a wish is not.
  • Dig from the solution the client names to the underlying need.
  • Give every requirement an ID, a priority, a fit-gap class and an acceptance test.

As-is and to-be process mapping

  • Map what happens today, with handoffs and workarounds, before designing what will happen.
  • Start from Zeyto's standard flow and change the process before the software.
  • Quantify the pain so the benefit is visible to the sponsor.

Fit-gap analysis against Zeyto

  • Classify every requirement and test it in Zeyto before calling it standard.
  • Most lines are configuration; real gaps must be named early.
  • Each gap needs a decision and an owner. Never promise a date for a custom request.

Scoping and estimating effort

  • Write what is in scope and, just as clearly, what is out.
  • Estimate by activity with three points, add contingency, then convert to price and calendar.
  • Data migration and client decision speed are the usual causes of overruns.

The Business Blueprint and sign-off

  • The blueprint is the signed design that all tests and changes are measured against.
  • Review it in a workshop, collect comments in one list and agree a review period.
  • Silence is not sign-off, and later changes go through change control.

Writing a proposal and statement of work

  • A SOW states scope, deliverables, exclusions, assumptions, price and change control.
  • Tie payments to accepted deliverables.
  • Precision in scope words prevents most disputes.

Running discovery workshops: key table

SessionWho attendsTopicsOutput
1 Sales and pricing (half day)Sales manager, two reps, sales admin, accountantQuotes, orders, discounts, credit, delivery, returnsAs-is sales process, pain points, requirement list
2 Purchasing and stock (half day)Purchasing manager, storekeeper, accountantOrdering, receiving, units, warehouses, stock countsAs-is purchase and stock process
3 Finance and VAT (half day)Accountant, finance managerChart of accounts, VAT, cheques, bank, month-endAccounting needs, opening balance approach
4 Management and IT (2 hours)Owner, IT contactReports, approvals, users, devices, backupsReport list, roles, infrastructure notes

Requirements gathering: key table

IDRequirementPrioritySourceFit-gapAcceptance test
R-01Sales invoices over AED 50,000 must be approved by the general manager before postingMustOwnerConfiguration: Approval RulesInvoice of AED 60,000 waits for approval; AED 40,000 posts
R-04Warn or stop sales to a customer over their credit limitShouldAccountantConfiguration: Credit ControlTest customer with AED 10,000 limit and AED 12,000 invoice is warned or refused
R-07Invoices print in English and ArabicMustSales managerConfiguration: print format and templatesPrint preview shows Arabic version
R-09Reps sell from the field with no signal and sync laterMustSales managerStandard: Field SalesOffline sale appears after Send now
R-12Owner sees yesterday's sales each morningShouldOwnerConfiguration: Daily Owner ReportReport arrives by e-mail at the set time

As-is and to-be process mapping: key table

StepAs-isPainTo-be in Zeyto
Receive orderWhatsApp message copied to a paper padLost or misread ordersSales admin enters a Sales Order (from a Quotation where used)
Check stockStorekeeper looks at an Excel sheetStale quantitiesStock seen per warehouse in Zeyto before promising a date
DeliverPaper slip signed by the customerUnbilled deliveriesDelivery Note made from the Sales Order; invoice follows from it
InvoiceTyped in a word-processor templateVAT errors, no link to stockSales Invoice pulled from the Delivery Note; VAT per line by tax code
CollectNotebook of who owes whatNo ageing, late chasingReceipts allocated to invoices; ageing report reviewed weekly

Scoping and estimating effort: key table

ActivityDays
Discovery and blueprint4
Configuration (O 4, M 6, P 8 gives 6.0)6
Data migration and reconciliation5
Testing and UAT support3
Training (4 sessions)4
Go-live and hypercare4
Project management2
Subtotal28
Contingency 15%4.2
Total32.2