Module 43 · Core · 9 min read

Retention held and released

You will be able to: Compute retention, the retention cap and the invoice for a certificate; Describe the release triggers and the approvals required; State the VAT time-of-supply point for retention and what to watch.

  • Read not done yet
  • Self-check: not taken not done yet
  • Lesson complete not done yet

Retention is the part of each certified amount the client keeps until the work is accepted and defects are fixed. In Zeyto Construction & Contracting it is held as a receivable in an append-only retention ledger, so the balance can always be traced to the bills that created it and the releases that cleared it.

Retention 10% on a certificate of AED 500,000 with 5% VATRetention withheld = 10% x 500,000 = 50,000. Billed before VAT = 500,000 - 50,000 = 450,000. VAT 5% on 450,000 = 22,500. Tax invoice total = 472,500, which is what the client pays (before any advance recovery). Held by the client: 50,000. The VAT on the retained 50,000, AED 2,500, is due later when the retention is released.

The cap

If the contract has a cap, retention stops when the total held reaches that share of the contract value. With a contract of AED 5,000,000 and a cap of 5%, the most that can be held is AED 250,000. If AED 220,000 is already held and the new certificate is AED 500,000, 10% would be 50,000 but only 30,000 of room remains, so the retention is 30,000. Taxable is 470,000, VAT 23,500 and the invoice 493,500.

The Retention screen listing the retention held from clients and to subcontractors with release status.

Retention: what is held and what can be released.

Retention: what is held and what can be released.

Releasing retention

  • Record a practical completion certificate (and later the end of the defects period). Practical completion and handover start the defects liability clock.
  • Request a release. At practical completion the contract share is claimed (50% of the retention held unless the contract says otherwise); at the end of the defects period the whole balance is claimed; a partial release takes an amount you type. A release can never exceed the retention held, less releases already waiting.
  • Two different people, neither the one who requested it, approve it.
  • Issue the release invoice. The retention is credited to the receivable and VAT is declared on that invoice.
The Retention report with the balances held by project.

Reports, Retention.

Reports, Retention.

With AED 100,000 held, a practical completion release is 50,000 plus VAT 2,500, an invoice of 52,500. The balance of 50,000 is claimed at the end of the defects period, with its own VAT.

VAT and the 12-month point

The Federal Tax Authority's real estate guide treats retention under the rules for continuous supplies of services: the supply date is the earliest of the retention being paid, a tax invoice being issued for it, or 12 months after the work was signed off as complete. It also says certification on its own does not create the date of supply. Zeyto declares the VAT on the retained part on the release invoice.

Watch outIf a retention stays unreleased for more than 12 months after sign-off, the FTA guidance can bring the VAT forward even without a release. Diary the 12-month date for every project and ask your tax adviser how to treat it. Do not assume the system raises it for you.
TipRetention you hold from subcontractors is a payable in the same ledger and follows the same release approvals. The two sides should be read together on the Retention report.

Walk it through

  1. Recompute the 500,000 example with 5% retention.
  2. Compute the capped retention if 240,000 is already held and the cap is 250,000.
  3. In the demo, open Retention and certificates on the Billing tab and find where a release is requested; note who may approve it.
Open the live demo

Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.

Key takeaways
  • Retention = certified gross x %, limited by the cap; VAT is on the part billed.
  • Releases need a certificate for the trigger, two approvers, then a release invoice with VAT.
  • Diary the 12-month sign-off point; the FTA guide can bring the supply date forward.

Check yourself

5 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.

1. The release of retention needs:

2. Certified gross is AED 500,000, retention 10%, VAT 5%. What is the tax invoice total?

3. Practical completion release of 50% of AED 100,000 retention held, plus VAT, is invoiced at:

4. Contract AED 5,000,000, retention cap 5%, AED 220,000 already held, certificate AED 500,000 at 10%. What retention is withheld?

5. Under FTA guidance, retention held unpaid for more than 12 months after sign-off can create a date of supply.

Practice questions for this module · Printable study sheet