The project and its breakdown (WBS)
You will be able to: Describe the fields of a project record and its status list; Build a breakdown of categories and items and say where cost, quantity and progress live; Calculate sell and cost amounts of items and the weighted progress of a project.
- Read not done yet
- Self-check: not taken not done yet
- Lesson complete not done yet
A project in Zeyto Construction & Contracting is one piece of work for one client. You create it from Projects with a name and, optionally, your own project number (otherwise the next number, such as P-00001, is taken). Saving creates a project centre with the same code, so documents can be tagged. The project card holds the client, consultant, project manager, key dates and a status.
The statuses, in the order a job normally moves, are enquiry, tender, planning, active, on hold, practical complete, defects period, closed and cancelled. Two controls on the card matter for money: the cost lock date (no cost may be posted on or before it) and the over-budget control (off, warn, approval or block, covered in module 4).
The breakdown
The breakdown (WBS, in the help for people who use the term) is one tree. A category groups other nodes and shows the sum of what is below it; an item is where quantities, rates, cost, material issues and progress are entered. Zeyto warns when a tree goes deeper than 6 levels and refuses beyond 12. You can copy a branch from the Category Master with Copy into project, after which the project no longer follows the master, or add nodes by hand.
- BOQ quantity, sell rate and unit cost are typed on an item.
- Sell amount is quantity times sell rate; cost amount is quantity times unit cost.
- Budget is then split by nature (material, own labour, machines, subcontract, third-party manpower, other).
- Progress is entered on items only and rolls up to the categories above.
Walk it through
- Sketch a breakdown of a villa with 3 categories and 8 items; mark which nodes are categories.
- For two items, compute sell amount and cost amount from your own quantities and rates.
- In the demo, open a project, then Structure, and compare an item's BOQ quantity, sell amount and progress with the roll-up on its category.
Public demo company, sign in as admin / demoAdmin123. Data refreshes nightly.
- Cost goes to items; categories only add up.
- Progress is weighted by sell value, not averaged.
- Statuses, the cost lock date and the budget control are set on the project card.
Check yourself
5 questions on this lesson. Not timed, not the exam, and you can try again. Score 60% or more, and read the lesson, to complete it.